A manager employed 100 programmers to complete a programming project in 120 days. If in 60 days only one-third of work is completed, how many additional programmers are needed to complete the project in time?
A manager employed 100 programmers to complete a programming project in 120 days. If in 60 days only one-third of work is completed, how many additional programmers are needed to complete the project in time? Correct Answer 100