Anil and Balbeer can finish a task in 3 days. They started working together, but after 2 days Anil got injured. Balbeer took 2 more days to finish the task. In how many days can Balbeer alone finish the same task?
Anil and Balbeer can finish a task in 3 days. They started working together, but after 2 days Anil got injured. Balbeer took 2 more days to finish the task. In how many days can Balbeer alone finish the same task? Correct Answer 6
Given:
Anil and Balbeer can finish a task = 3 days
They worked together = 2 days
Balbeer took more days to finish the task = 2
Calculation:
LCM of 2 and 3 is 6
Anil and Balbeer do work = 6/3
⇒ 2 units/day
Anil and Balbeer 2 days work = 2 × 2 = 4 units
Work left = 6 – 4 = 2 units
Remaining work is done by Anil in 2 days
Anil's per day work = 2/2 = 1 unit/day
Balbeer's per unit work = (Anil + Balbeer)'s work – Anil's work
⇒ 2 – 1 = 1 unit/day
Balbeer alone can finish the same task = 6/1
⇒ 6 days
∴ Balbeer alone can finish the same task is 6 days