Consider the following phases of project management: 1. Identification 2. Formulation 3. Appraisal 4. Implementation Which of the above phases are relevant, sequentially?
Consider the following phases of project management: 1. Identification 2. Formulation 3. Appraisal 4. Implementation Which of the above phases are relevant, sequentially? Correct Answer 1, 2, 3 and 4
Explanation:
There are 7 stage to project management but there are five stage mainly.
(a) Project identification
(b) Project preparation (project formulation)
(c) Project appraised
(d) Negotiation
(e) Project approval
(f) Project planning
(g) Project implementation
মোঃ আরিফুল ইসলাম