1 Answers
50 daily workers done by 40 day's
∴ 1 daily workers done by 40×50 days
∴ 30 daily workers done by 40×50/30= 200/3 days.
In 2 days, the worked done by (1/40+3/200)= 1/25 parts.
1/25 parts done by 2 days
∴ 1 part done by 25×2= 50 days.
So, days will be required in (50-40)= 10 days. (answered)