1. The maximum time which an activity might require
  2. The average time required for a job
  3. The most probable time considering all conditions
  4. The minimum time in which an activity can possibly be accomplished
4 views

1 Answers

Answer: Option 1

Pessimistic time is a concept used in the program evaluation and review technique (PERT). It represents the longest estimated time period within which a task is likely to be completed, and is used in project planning.