The time taken by A and B to finish a work is 12 days. The time taken by B and C to finish double the previous work is 28 days. The ratio of the efficiencies of A and C is 3 : 1. What is the time (in days) taken by C alone to finish the work?
The time taken by A and B to finish a work is 12 days. The time taken by B and C to finish double the previous work is 28 days. The ratio of the efficiencies of A and C is 3 : 1. What is the time (in days) taken by C alone to finish the work? Correct Answer 168
Given:
The time taken by A and B to finish a work is 12 days. The time taken by B and C to finish double the previous work is 28 days. The ratio of the efficiencies of working of A and C is 3 : 1.
Concept used:
The ratio of time taken to finish the work is inversely proportional to the ratio of their efficiencies.
Calculation:
The time taken by A and B to finish a work is 12 days.
⇒ 1/a + 1/b = 1/12 ….(i)
The time taken by B and C to finish double the previous work is 28 days
So, the time taken by B and C to finish the work is 14 days.
⇒ 1/b + 1/c = 1/14 ….(ii)
Comparing 1/b from both the equations, we get,
⇒ 1/b = 1/14 – 1/c = 1/12 – 1/a
⇒ 1/a – 1/c = 1/84
Also, the ratio of the efficiencies of working of A and C is 3 : 1.
The ratio of time taken will be 1 : 3
Let the time taken by A and C be ‘t’ and ‘3t’ respectively.
⇒ 1/t – 1/(3t) = 1/84
⇒ 2/(3t) = 1/84
⇒ t = 56 days
∴ C takes (56 × 3) days = 168 days