30 men can complete a work in 38 days. They work for 25 days then 5 more men joined the group and the work was finished 1 day earlier. How many days would it have been delayed if 5 more men were not joined the group?
30 men can complete a work in 38 days. They work for 25 days then 5 more men joined the group and the work was finished 1 day earlier. How many days would it have been delayed if 5 more men were not joined the group? Correct Answer 1 day
Given:
30 men can complete a work in 38 days. They work for 25 days then 5 more men joined the group and the work was finished 1 day earlier
Concept:
We will use Man-day principle for doing this.
Calculation:
Let one man do 1 unit of work in one day.
Then 30 men in 38 days do 1140 units work.
Total work = 1140 unit
Work done in 1st 25 days = 30 × 25
Remaining work = 30 × 13
Work was completed in the next 12 days
Those who are already working = 30
Their work in 12 days = 30 × 12
Remaining work = 30 unit which is done by 5 men
So, Work done by these man in one day = (30/5)/12 = 1/2 unit
If 5 men had not joined time taken would have been less than 1 day.