If 12 persons working 12 hours a day dig 12 meters of a tunnel in 12 days how many men are required to dig additional 4 meter of the tunnel (of the same dimension) given that they work 4 hours a day for 4 day?
If 12 persons working 12 hours a day dig 12 meters of a tunnel in 12 days how many men are required to dig additional 4 meter of the tunnel (of the same dimension) given that they work 4 hours a day for 4 day? Correct Answer 36
Given:
12 persons working 12 hours a day dig 12 meters of a tunnel in 12 days
Formula Used:
Man – day formula
(m1× d1× h1)/w1 = (m2 × d2 × h2)/w2
Where m1, m2 is number of persons working
d1, d2 is number of days taken
h1, h2 is number of hours
w1, w2 is the units of work done
Calculation:
Let the number of men required be x
(12 × 12 × 12)/12 = (x × 4 × 4)/4
⇒ x = 36
∴ Number of men required be 36