If 15 men construct a building in 50 days, then in how many days can 10 men construct a building?

If 15 men construct a building in 50 days, then in how many days can 10 men construct a building? Correct Answer 75 days

Given:

Number of men = 15

Number of days = 50

Formula used:

M1 T1 = M2 T2

Where M1; M2; T1 and T2 represents number of men and time

Calculation:

15 × 50 = 10 × T2

⇒ T2 = (15 × 50)/10

⇒ T2 = 75

∴ 75 days are required to construct a building by 10 men.