Given:
Ramesh, Suresh, and Kamlesh take 10, 15, and 30 days respectively.
Calculation:
Suppose the total work be the LCM of (10, 15, 30) be 30 unit
So, the efficiency of Ramesh = 30/10 = 3 units/day
Efficiency of Ramesh = 30/15 = 2 units/day
And, efficiency of Kamlesh = 30/30 = 1 unit/day
Work Done in 3 days (1 day of all three together + 2 days of Ramesh’s work) = 2 × 3 + (3 + 2 + 1) = 12 units
⇒ Work done in 3 days = 12 units
⇒ Wok done in 6 days= 24 units
And on 7th and 8th day Ramesh will work alone and perform total work = 24 + 3 + 3 = 30 units