5 laborers working 12 hours a day can complete a piece of work in 30 days. In how many days will it take 15 laborers to do half the work, working 12 hours a day?
5 laborers working 12 hours a day can complete a piece of work in 30 days. In how many days will it take 15 laborers to do half the work, working 12 hours a day? Correct Answer 5 days
Given:
5 labours working 12hrs/day can complete the work in = 30 days
Calculation:
Required number of days = x
According to the question,
⇒ (5 × 12 × 30) × (1/2) = (15 × 12 × x)
⇒ 180x = 900
⇒ x = 5
∴ 5 days will be required.