12 men can complete a painting work in 8 days. However, 16 women can complete the same painting work in 12 days. 8 men started painting the house. After 6 days of painting, 2 men were replaced by 4 women. Now how many days will they take to complete the remaining painting?
12 men can complete a painting work in 8 days. However, 16 women can complete the same painting work in 12 days. 8 men started painting the house. After 6 days of painting, 2 men were replaced by 4 women. Now how many days will they take to complete the remaining painting? Correct Answer 6
Given:
12 men can complete a painting work in 8 days.
16 women can complete the same painting work in 12 days
8 men started painting the house.
After 6 days of painting, 2 men were replaced by 4 women
Formula used:
Work = Efficiency × Time
Calculation:
12 men can complete a painting work in 8 days = (12 × 8) = 96
16 women can complete the same painting work in 12 days = (16 × 12) = 192
The ratio of men and women = (96 : 192)
⇒ 1 : 2
Total work = (12 × 1 × 8) = 96 units
Now,
8 men started the painting for 6 days = (8 × 1 × 6) = 48 units
Remaining work = (96 – 48) = 48 units
2 men were replaced by 4 women = (4 × 2) = 8 women
Now,
Time taken to complete the remaining painting = (48/8)
⇒ 6 days
∴ The required time is 6 days