Which one of the following is a point in time when certain conditions have been fulfilled, such as the start or completion of one or more activities?
Which one of the following is a point in time when certain conditions have been fulfilled, such as the start or completion of one or more activities? Correct Answer Event
Concept:
Activity: An activity is an actual work to be done in a project. It indicates time and resources by arrows.
Network: The graphical representation of activities is called a network. This deals with events and activities and considers both cost and time.
A network depicts the relationship between different activities by means of arrows in a logical sequence.
Event: Each activity is placed within two circles or nodes known as an event. A node (event), denoted by nodal points, marks a start and completion of an activity.