Given:

Aakash can complete a work in = 12 days

Birwa can complete a work in = 15 days

Chirag can complete a work in = 10 days

Chirag left the work 5 days before the work was completed

Aakash left the work 3 days before the work was completed

Calculation:

Let the whole work be 1.

Let the days required to do the whole work be x.

Aakash’s 1 day’s work = 1/12

Birwa’s 1 day’s work = 1/15

Chirag’s 1 day’s work = 1/10

⇒ (x - 3)/12 + x/15 + (x - 5)/10 = 1

⇒ 5(x - 3) + 4x + 6(x - 5) = 60

⇒ 15x – 45 = 60

⇒ 15x = 105

⇒ x = 7

∴ to complete the whole work 7 days are required.