If an efficiency variance is 200 units and actual input quantity is 750 units, then budgeted input quantity will be
If an efficiency variance is 200 units and actual input quantity is 750 units, then budgeted input quantity will be Correct Answer 550 units
Budgeted input quantity = Actual input quantity - Efficiency variance= 750 - 200 = 550 units.