A dummy activity is used in PERT network to describe the A Precedence relationship B Resource idleness C Resource restriction D Necessary time delay A dummy activity is used in PERT network to describe the Correct Answer Precedence relationship Bissoy MCQ Team Chemical Engineering Chemical Engineering Basics