In resources levelling A Total duration of project is reduced B Total duration of project is increased C Uniform demand of resources is achieved D Cost of project is controlled In resources levelling Correct Answer Uniform demand of resources is achieved Bissoy MCQ Team Civil Engineering Construction Planning And Management