The reduction in project time normally results in
A
Decreasing the direct cost and increasing indirect cost
B
Increasing the direct cost and decreasing the indirect cost
C
Increasing the direct cost and indirect cost both
D
Decreasing the direct cost and indirect cost both
Correct Answer: Increasing the direct cost and decreasing the indirect cost