If the toll is to be collected through and outsourced agency by allowing a maximum 10% commission how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with Rs. 4,910 crores?

If the toll is to be collected through and outsourced agency by allowing a maximum 10% commission how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with Rs. 4,910 crores? Correct Answer Rs. 5,401crores

Let the amount permitted to be collected = Rs. x
$$\eqalign{& x = 4910 \times \left( 1 + \frac{10}{100} \right) \cr& x = \left( 4910 \times \frac{110}{100} \right) \cr& x = 491 \times 11 \cr& x = \text{Rs. }5401 \text{ crores} \cr} $$