Dumper arrives at a shovel at a constant rate of 10 per hour. The service rate is constant at 15 per hour. At a time, the expected number of dumpers in the queue is
Dumper arrives at a shovel at a constant rate of 10 per hour. The service rate is constant at 15 per hour. At a time, the expected number of dumpers in the queue is Correct Answer 2