The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is
A
1.00 m<sup>3</sup>
B
1.25 m<sup>3</sup>
C
1.50 m<sup>3</sup>
D
1.75 m<sup>3</sup>
Correct Answer: 1.25 m<sup>3</sup>