Crash project duration is obtained by summing the

A Normal durations for all the activities
B Crash durations for all activities
C Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
D Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

Correct Answer: Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities