For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

A 1
B 2
C 3
D 4

Correct Answer: 4

This is the correct answer. In construction project management using a bar chart (Gantt chart), each activity is represented by a horizontal bar. The activities mentioned in the question include:

1. Supply of materials for concrete
2. Formwork, reinforcing, and placing of concrete
3. Removal of formwork
4. Curing of concrete
Each of these activities requires a separate bar on the chart.

Related Questions

The ratio of the diameter of reinforcing bars and the slab thickness is
The minimum horizontal distance between two parallel main reinforcing bars, is
The bars in a bar chart are represented by the
Gantt chart (or Bar chart) is helpful in
When a bar of length '$$l$$' and diameter 'd' is rigidly fixed at the upper end and hanging freely, then the total elongation produced in the bar due to its own weight is (where w = Weight per unit volume of the bar)
A chart comprised of bars, each representing a period of time, is called a

Next steps