The essential condition for the decompression of an activity is that

A The project time should change due to decompression
B After decompression the time of an activity invariably exceeds its normal time
C An activity could be decompressed to the maximum extent of its normal time
D None of the above

Correct Answer: An activity could be decompressed to the maximum extent of its normal time

The essential condition for the decompression of an activity is that An activity could be decompressed to the maximum extent of its normal time

Related Questions

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
For seccessful operation of two single phase transformer connected in parallel, the most essential condition is that their
The essential condition for the promotion of higher activities of life is
The essential condition for parallel operation of two D.C. generators is that they have
Which of the following is not an essential condition of pure competition?
Cohesion and coherence is essential in :

Next steps