20 men complete one-third of piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days?

20 men complete one-third of piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? Correct Answer 12

"পরাজিত প্রার্থী পায় x টি ভোট জয়ী “ “ (x + 476) “ "" শর্তমতে, 2x + 476×84100 = x + 476⇒42x + 476×21 = 25x + 476×25⇒17x = 47625 - 21⇒x = 476×417∴x = 112∴ মোট ভোটার 2×112 + 476 = 700

Related Questions