Mr. Jamal employed 50 workers to finish a work within 30 days. After 20 days he found out that only 50% of the work had been completed. How many additional workers will Mr. Jamal need to finish the work in time?
Mr. Jamal employed 50 workers to finish a work within 30 days. After 20 days he found out that only 50% of the work had been completed. How many additional workers will Mr. Jamal need to finish the work in time? Correct Answer 50
Within 20 days, he has finished 50% work by 50 people . so to finish within 10 days he will need 100 people ( 100 - 50) = 50 people