The value of K and H should be determined according to the ARL required for the corresponding cusum chart.

The value of K and H should be determined according to the ARL required for the corresponding cusum chart. Correct Answer True

ARL value tells about the time until the next out-of-control signal. So it is also an estimate to predict the type I error possibility. Hence, K and H values should be determined according to the ARL required.