Find the office cost (in Rs.) of 250 bolts and nuts if the factory cost is Rs.200 and total labour cost is Rs.200. Consider office overheads as 30% of the total labour cost.
Find the office cost (in Rs.) of 250 bolts and nuts if the factory cost is Rs.200 and total labour cost is Rs.200. Consider office overheads as 30% of the total labour cost. Correct Answer 260
Given, 250 bolts and nuts Factory cost = Rs.200 Total labour cost = Rs.200 Office overheads = 30% of total labour cost Office cost = Factory cost + office on cost = 200 + 0.3 × 200 = Rs.260/-