Which one of the following method of construction is adopted when low clearance is required below the deck?

Which one of the following method of construction is adopted when low clearance is required below the deck? Correct Answer Stagging method

The staging method is adopted when low clearances required below the deck and supporting formwork does not interfere with the traffic and this method facilitates rapid construction by maintaining correct geometry of the structure with relatively low cost.