For the removal of nitrogen completely through Activated Sludge Process (ASP) what would be the Solid retention time considered?
For the removal of nitrogen completely through Activated Sludge Process (ASP) what would be the Solid retention time considered? Correct Answer 1-2 days
For the complete removal of Nitrogen through ASP, the solid retention time considered is 3-18 days. However, this depends on the temperature. In case the temperature is very low, then the solid retention time considered would be around 15-18 days. For higher temperatures, lower solid retention time is considered.
মোঃ আরিফুল ইসলাম
Feb 20, 2025