For purely rigid streams, the foundation of the bridge substructure is taken above the bed.
For purely rigid streams, the foundation of the bridge substructure is taken above the bed. Correct Answer False
From theoretical considerations, there will be no scouring and the foundation of the bridge sub-structure will have to be taken below the bed by a nominal amount not by scour considerations. It is done so as to provide sufficient grip on them.