If m men can paint a house in d days, how many days will it take m+2 men to paint the same house?
A
d+2
B
(m+2)/md
C
md/(m+2)
D
d+m+2
Correct Answer: md/(m+2)
m men can paint a house in d days, .',1 men can paint a house in md days so, (m + 2) men would finish the same job in = md/(m + 2) ans: md/(m + 2)