Match the column. a. Detailed estimate 1. Estimate of additional works during the process b. Supplementary estimate 2. Prepared for approx. rates initially c. Revised estimate 3. Includes details and cost of everything d. Rough estimate 4. Prepared when the costs exceed more than 5%
Match the column. a. Detailed estimate 1. Estimate of additional works during the process b. Supplementary estimate 2. Prepared for approx. rates initially c. Revised estimate 3. Includes details and cost of everything d. Rough estimate 4. Prepared when the costs exceed more than 5% Correct Answer a - 3, b - 1, c - 4, d - 2
Explanation:
1. Supplementary estimate: While a work in progress some additional works may be thought necessary for the development of a project which was not foreseen when the original estimate was framed, the estimate when prepared to cover all such works are known as a supplementary estimate
2. Detailed Estimate: Includes the quantities and cost of everything required for satisfactory completion of work.
3. Revised estimate: When sanctioned estimate is exceeded by more than 5% either from rates being found insufficient due to change in the price level or from any cause except important structural alterations.