Which of the following quality gurus proposed the plan-do-check-act (PDCA) cycle for quality improvement activity?

Which of the following quality gurus proposed the plan-do-check-act (PDCA) cycle for quality improvement activity? Correct Answer W Edwards Deming

Explanation:

  • The original founder of the PDCA cycle (Plan-Do-Check-Act) is Walter A. Shewhart. W Edwards Deming promoted the use of the PDCA cycle forquality improvement and later changed it to the PDSA cycle (Plan-Do-Study-Act).
  •  
  •  
  •  
  •  
  •  
  •  
  •  

Plan-Do-Check-Act (PDCA) cycle:

  • Every organization regardless of the sector emphasize quality improvement on a continuous basis.
  • There is no set rule or standard method to implement quality improvement initiatives.
  • The most commonly used total quality management (TQM) tools are graphical tools that are effective in improving quality.
  • The conceptual basis for implanting various tools is Deming’s Plan-Do-Check-Act (PDCA) cycle, also called the Deming wheel.
  • Deming wheel is a repetitive cycle of quality improvements resulting from continuous incremental turns of the wheel to achieve a higher level of quality over time the period as shown in the figure.