Option 2 : NTPC
The correct answer is NTPC.
- The memorandum of understanding was signed between NTPC Renewable Energy Limited (NTPC REL) and the government of Rajasthan to mark another step toward achieving the Renewable Capacity addition targets of NTPC.
- At the group level, NTPC aims to have a 60 GW renewable power generation capacity by 2032.
-
Energy minister Bhanwar Singh Bhati said It has been agreed to make a private investment by the state government to develop an ultra mega renewable energy power park of 10,000 MW capacity in Rajasthan.
National Thermal Power Corporation Limited
- It is engaged in the generation of electricity and allied activities. It is a statutory corporation incorporated under the Companies Act 1956 and is under the ownership of the Ministry of Power.
- The company has developed a long-term plan to become a 128000 MW company by 2032. 10000 MW of Solar PV capacity by 2032.