Option 1 : Only 1 and 2
The correct answer is option 1 i.e. Only 1 and 2,
- Guri Hydroelectric project and the reservoir are located 100km upstream of the Caroni River in Necuima Canyon in Orinoco, Venezuela.
- This power project is one of the biggest power plants in the world and its capacity for 10,200MW.
- The Guri power plant was inaugurated in 1986 AD and meets the need of approximately 73% of the country’s energy requirements.
- The Itaipu hydroelectric dam is located on the Parana River the border between Brazil and Paraguay.
- The Coca Codo Sinclair hydroelectric project supplying approximately 44% of the country’s electricity needs.