The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as?
Total float
Free float
Interfering float
Independent float
LohaHridoy
0
Edit
5
views
2025-01-04 04:42
1
Answers
AhmedNazir
Answer: Option 4
Let'
0
Thanks
5
views
Answered
2022-09-01 13:21
Report
Edit
Call
Related Questions
Directions : In each of the following questions a statement is given, followed by two conclusions. Give answer : Statement : Nobody can predict as to how long our country would take to contain the unfortunate and disastrous terrorist activities. Assumptions : I. It is impossible to put an end to terrorist activities. II. Efforts to control the terrorist activities are on.?
1 Answers
5
Views
By the time they reach adulthood, most people can perform many different activities involving motor skills. Motor skills involve such diverse tasks as riding a bicycle, threading a needle, and cooking a dinner. What all these activities have in common is their dependence on precision and timing of muscular movement. This paragraph best supports the statement that?
1 Answers
7
Views
Out of eight crew members three particular members can sit only on the left side. Another two particular members can sit only on the right side. Find the number of ways in which the crew can be arranged so that four men can sit on each side.?
1 Answers
7
Views
Directions : Following question consists of a statement followed by three arguments I, II and III . You have to decide which of the arguments is a STRONG arguments and which is a WEAK Argument. Statement : Should the parliamentary elections in India be held every three years as against five years at present Arguments : I. No. This will enhance wastage of money and resources. II. Yes. This will help the voters to change non-performing representatives without much delay. III. No. The elected representatives will not have enough time to settle and concentrate on developmental activities.?
1 Answers
5
Views
The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as?
1 Answers
4
Views
The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as?
1 Answers
4
Views
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as?
1 Answers
4
Views
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as?
1 Answers
4
Views
Which of the following is/are true of world time zones I. The world is divided into thirty time zones II. All time zones of the world are described in term of the number of hours difference between the standard meridian of that zone and the Greenwich Meridian III. All countries have more than one time zone IV. The time for all places east of Greenwich is designated slow, and time for all places left of Greenwich is designated fast?
1 Answers
5
Views
Due to enormous profits involved in smuggling, hundreds of persons have been attracted towards this anti-national activity. Some of them became millionaires overnight. India has a vast coastline both on the Eastern and Western Coast. It has been a heaven for smugglers who have been carrying on their activities with great impunity. There is no doubt, that from time to time certain seizures were made by the enforcement authorities, during raids and ambush but even allowing these losses the smugglers made huge profits. The passage best supports the statement that:?
1 Answers
6
Views
কোরআন
হাদিস
চাকুরি প্রস্তুতি
বিশ্ববিদ্যালয় ভর্তি
মেডিকেল SBA
12
এইচএসসি
10
এসএসসি
8
জেএসসি
এক্সাম দিয়ে মেধা যাচাই করুন
Job Preparation (1125)
Admission (754)
এসএসসি (10)
এইচএসসি (5)
Login Required
You need to log in to continue.
Login
Cancel
Download Required
You need to download the app to make a call.
Download
Cancel