Answer: Option 1
When slack of an activity is positive - it represents a situation where extra resources are available and the completion of the project is not delayed. When slack of an activity is negative- it represents that a program falls behind schedule and additional resources are required to complete the project in time. When slack of an activity is zero - the activity is critical and any delay in its performance will delay the completion of the whole project.