A push through system, according to which goods are manufactured for finished inventory solely, on basis of forecasted demand can be classified as

A in-time production
B materials requirement planning
C on-time production
D pull strategy of production

Correct Answer: materials requirement planning

A push through system, according to which goods are manufactured for finished inventory solely, on basis of forecasted demand can be classified as materials requirement planning. Material requirements planning (MRP) is a system for calculating the materials and components needed to manufacture a product.