Pick up the correct step used for scheduling a project by C.P.M.
A
A project is divided into various activities
B
Required time for each activity is established
C
Sequence of various activities is made according to their importance
D
All of the above
Correct Answer: All of the above
For scheduling a project by C.P.M.- A project is divided into various activities
- Required time for each activity is established
- Sequence of various activities is made according to their importance