Pick up the correct step used for scheduling a project by C.P.M.

A A project is divided into various activities
B Required time for each activity is established
C Sequence of various activities is made according to their importance
D All of the above

Correct Answer: All of the above

For scheduling a project by C.P.M.
- A project is divided into various activities
- Required time for each activity is established
- Sequence of various activities is made according to their importance