The technique for establishing and maintaining priorities among the various jobs of any project is known as

The technique for establishing and maintaining priorities among the various jobs of any project is known as Correct Answer Critical ratio scheduling

The critical ratio (CR) is calculated by dividing the time remaining until a job's due date by the total shop time remaining for the job, which is defined as the setup, processing, move, and expected waiting times of all remaining operations, including the operation being scheduled.