The critical path of a network represents

A The minimum time required for completion of project
B The maximum time required for completion of project
C Maximum cost required for completion of project
D Minimum cost required for completion of project

Correct Answer: The minimum time required for completion of project

The critical path of a network represents The minimum time required for completion of project

Related Questions

For completion of a project, the critical path of the network represents
When the addenda on pinion and wheel is such that the path of approach and path of recess are half of their maximum possible values, then the length of the path of contact is given by (where r = Pitch circle radius of pinion, R = Pitch circle radius of wheel and $$\varphi $$ = Pressure angle)
You are adding a new server to your network. The network uses TCP/IP. The new server will provide users with dial-up access to network resources. The data link communications protocol you choose for dial-up access must allow you to provide secure authentication. Which protocol should you choose?
Critical path of the PERT chart is:
Critical path moves along the activities having total float of

Next steps