30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days?
A
24
B
12
C
36
D
48
Correct Answer: 24
16 days required for = 30 men 1 " " " = 30×16 men 20 " " " = (30×16)/20 men = 24 men