Flexible budget amount is $57000 and flexible budget variance is $14000, then actual result amount will be
Flexible budget amount is $57000 and flexible budget variance is $14000, then actual result amount will be Correct Answer $71,000
Actual result = Flexible budget amount + Flexible budget variance= $57000 + $14000 = $71,000