A and B together can complete a piece of work in 12 days, B and C can do it in 20 days and C and A can do it in 15 days. A , B and C together can complete it in.
A
12 days
B
6 days
C
8 days
D
10 days
Correct Answer: 10 days
A & B can do in 1 day = 1/12 work B & C can do in 1 day = 1/20 work C & A can do in 1 day = 1/15 work 2(A&B&C) can do in 1 day = 1/12 + 1/20 + 1/15 = 12/60 = 1/5 work. A&B&C can do in 1 day = 1/(5 × 2) = 1/10 work. Required number of days = 1/(1/10) = 10 days. Ans: D