In Belgium method of tunnelling
A
Construction of side walls is completed before invert and roof arch are built
B
Construction of roof arch is completed before side walls and inverts are built
C
Construction of invert is completed before side walls and roof arch are built
D
Construction of invert and side walls is completed before roof arch is built
Correct Answer: Construction of roof arch is completed before side walls and inverts are built