In the penetration macadam construction, the bitumen is
A
Sprayed after the aggregates are spread and compacted
B
Premixed with aggregates and then spread
C
Sprayed before the aggregates are spread and compacted
D
None of the above
Correct Answer: Sprayed after the aggregates are spread and compacted