For under water concreting.
A
At least 10 percent more cement is required as compared to dry conditions
B
The volume of coarse aggregates shall not be less than one and half times and not more than twice that of fine aggregate
C
De-watering by pumping is not done or until 24 hours thereafter
D
All the above
Correct Answer: All the above