Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation $$\frac{{{\text{Cv}}}}{2}$$ to achieve the same degree of consolidation is
Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation $$\frac{{{\text{Cv}}}}{2}$$ to achieve the same degree of consolidation is Correct Answer 3 months