There are two processes P1 and P2, whose periods are 50 and 100 respectively. P1 is assigned higher priority than P2. The processing times are t1 = 20 for P1 and t2 = 35 for P2. Is it possible to schedule these tasks so that each meets its deadline using Rate monotonic scheduling?
There are two processes P1 and P2, whose periods are 50 and 100 respectively. P1 is assigned higher priority than P2. The processing times are t1 = 20 for P1 and t2 = 35 for P2. Is it possible to schedule these tasks so that each meets its deadline using Rate monotonic scheduling? Correct Answer yes